Ethiopian Airlines Group has appointed KPMG as financial adviser for its Bishoftu International Airport project, a multi‑billion‑dollar initiative aimed at creating one of Africa’s largest aviation hubs.
The airport, located roughly forty kilometres southeast of Addis Ababa, is designed to handle up to 110 million passengers annually, more than four times the airline’s current capacity, and accommodate extensive cargo operations across multiple runways.
KPMG International Limited, British multinational professional services network, will work alongside the African Development Bank, serving as mandated lead arranger, and Dar Al‑Handasah Consultants, acting as technical adviser. The airline said a legal adviser is expected to be appointed shortly to complete the advisory team.
The network is part of the world’s “Big Four” accounting and advisory firms, alongside Deloitte, PricewaterhouseCoopers and Ernst & Young. The network provides audit, tax, advisory, and financial consulting services to governments, corporations, and institutions across sectors.
The project’s financing structure is planned as a ring‑fenced, limited‑recourse arrangement, with revenues channelled into a dedicated offshore account governed by a lender-approved cashflow waterfall. Officials said the use of blended finance will channel concessional capital to reduce risk for private investors, while guarantees from the AfDB and other multilateral lenders are expected to ease borrowing costs.
The debt-to-equity ratio is projected at 70 to 30. Ethiopian Airlines said financing mobilisation has already begun, with 59 financial institutions engaged, 42 signing non‑disclosure agreements, and 12 submitting letters of interest. Last year, Finance Minister Ahmed Shide announced that 4.8 billion US dollars had been pledged towards the airport project.
Selection of coordinating export credit agency banks is underway.
The project includes an offsite rail link connecting Bole International Airport and Bishoftu Mega‑Airport, with an estimated cost of 954 million US dollars.
Alongside the infrastructure, the airport development includes a resettlement and livelihood restoration programme. Affected households are being organised into cooperatives to participate in new businesses, with an estimated programme cost of 350 million US dollars. Land acquisition and resettlement costs to date total roughly 741 million US dollars.
Construction is being executed in phases. The lump-sum turnkey (LSTK) component is valued at 8 billion US dollars, contributing to a total project estimate of 12.5 billion US dollars. Early works, awarded to three contractors for 620 million US dollars, are expected to be completed by December 2026.
Dar Al‑Handasah Consultants has submitted a comprehensive package including the master plan, financial feasibility report, environmental and social assessments, geotechnical investigations, concept designs for terminal, airside and landside infrastructure, cargo and MRO facilities, transport links to Bole International Airport, fuel farm, utilities, cost estimates, and packaging structure. A consortium of international firms, including Zaha Hadid Architects, is contributing to terminal and infrastructure design.
Ethiopian Airlines said the airport is intended to strengthen Ethiopia’s position as a continental aviation hub, integrating passenger, cargo, and logistics operations while addressing social and economic participation for affected communities.
The airline said Bole International Airport, which currently handles around 25 million passengers annually, is facing congestion due to the growth of Africa’s largest carrier. Once Bishoftu Mega‑Airport becomes operational, Ethiopian Airlines plans to restrict Bole International to domestic flights, freeing capacity for the new hub to manage international operations.