Ethiopia has signed a 3 billion birr agreement to rehabilitate and modernise electricity infrastructure in three regional cities, as the country seeks to improve the reliability of power distribution while expanding access to electricity.
The agreement was signed between Ethiopian Electric Utility (EEU) and engineering and procurement firms Alfa and Capital for a power network rehabilitation project covering the cities of Ambo, Nekemte and Assosa.
The project, financed through 3 billion birr in World Bank support, is scheduled for completion within two years, according to Ethiopian Electric Utility.
EEU Chief Executive Getu Geremew said the investment is intended to improve the quality and reliability of electricity supply in urban areas, enabling customers to receive more dependable power services. He said the project should be completed within the agreed timeframe and according to the required technical standards.
The rehabilitation programme includes the upgrading of 325 kilometres of medium-voltage electricity distribution lines to strengthen the network and improve system capacity. The utility said the works are expected to reduce power interruptions and technical losses across the three cities.
The project also includes the rehabilitation and upgrading of 235 distribution transformers. Of these, 70 will be upgraded in Ambo, 121 in Nekemte and 44 in Assosa.
Ethiopia has expanded electricity generation capacity significantly over the past decade through large hydropower investments, including the Grand Ethiopian Renaissance Dam. However, ageing distribution infrastructure and network constraints have continued to affect the reliability of electricity supply in many parts of the country, prompting increased investment in transmission and distribution systems alongside generation projects.
The latest investment forms part of broader efforts to modernise Ethiopia's electricity network and improve service reliability as electricity demand continues to rise from households, businesses and industrial users.