The project company is seeking contractors to manufacture, transport and install 200,000 litres of fuel-storage capacity at its West Wollega mine site as development activity accelerates.
Tulu Kapi Gold Mine Share Company has launched procurement for fuel-storage infrastructure at its planned gold mine in western Ethiopia, adding to signs of increasing site activity as the long-delayed project moves closer to full-scale construction.
The company is seeking contractors to manufacture, transport and install four above-ground fuel-storage tanks, each with a capacity of 50,000 litres, giving the planned facility total storage capacity of 200,000 litres.
Tender documents issued on August 20 show that the company is procuring the manufacturing and installation works separately, with bids for both contracts due on September 4.
The installation contract covers loading the tanks at the manufacturer’s facility in Addis Ababa, transporting them by heavy vehicle to the Tulu Kapi mine site in West Wollega, offloading and positioning the units and completing associated electromechanical works.
The scope includes fuel delivery and suction piping, integration with fuel dispensers, automated tank-gauging systems, electrical grounding, explosion-proof wiring and final commissioning.
A separate contract covers the design and structural engineering of the tanks, procurement of raw materials, fabrication, testing, painting and internal lining.
The relatively routine infrastructure procurement is significant because it comes as Tulu Kapi Gold Mine Share Company, the Ethiopian subsidiary of London-listed KEFI Gold and Copper, begins moving from financing and contracting arrangements toward physical mine development.
In June, KEFI signed a mining services agreement worth more than 400 million US dollars with BCM Group covering mining operations during the project’s initial nine-year mine life.
Under the agreement, BCM will provide the mining fleet, train locally recruited operators and carry out mining operations under the supervision of Tulu Kapi Gold Mine Share Company. The contractor had already mobilised to Ethiopia for bulk earthworks when the agreement was announced.
The more than 400 million US dollars mining services deal is the largest operating contract awarded for Tulu Kapi and is separate from the capital expenditure required to construct the mine itself.
Development activity is now advancing across several components of the project, involving mining contractors, equipment suppliers, lenders and government agencies.
Tulu Kapi is backed by a 240 million US dollars senior secured project debt facility from the Eastern and Southern African Trade and Development Bank and Africa Finance Corporation.
The financing has been committed, although initial drawdown remains subject to completion of lender conditions, including technical, security and completion requirements as well as finalisation of KEFI’s share of construction funding.
The Ethiopian government is separately responsible for key supporting infrastructure, including connecting the mine to the national electricity grid and constructing an all-weather access road linking the site with the main highway.
KEFI is targeting commissioning of the mine in late 2027.
Located in West Wollega Zone in the Oromia region, Tulu Kapi is among Ethiopia’s most advanced large-scale gold developments and has spent more than a decade moving through financing, security and project-development hurdles.
The latest tenders do not disclose the estimated value of the fuel-storage contracts. Their launch, however, adds to a growing pipeline of procurement, contracting and site works around Tulu Kapi after years in which construction was repeatedly delayed.
Contractors interested in the fuel-storage works have until September 4 to submit technical and commercial proposals.
