Canaan Inc., the US-listed bitcoin mining and computing infrastructure company, had 4.96 exahashes per second (EH/s) of installed computing power in Ethiopia at the end of July, accounting for about one-third of its global installed mining capacity, according to the company’s latest unaudited operating update.
The figure places Ethiopia among Canaan’s largest mining locations, although the company did not disclose the locations of its Ethiopian facilities.
Canaan operated 12 active mining projects globally at the end of July, with total operating computing power of 14.24 EH/s and installed computing power of 14.89 EH/s. Its two Ethiopian projects accounted for 4.96 EH/s of installed capacity, compared with 4.90 EH/s of operating capacity across four projects in the Americas.
However, Canaan said in its July update that mining operations in Ethiopia had been paused. The company did not explain the reason for the suspension or say when operations would resume.
The Ethiopian facilities nonetheless remained part of Canaan’s installed mining infrastructure, with 4.96 EH/s of installed computing power and no additional capacity listed as under development.
Globally, Canaan mined 46 bitcoins in July, taking its cryptocurrency holdings at the end of the month to 1,917 BTC and 3,952 ETH. The company did not provide a country-by-country breakdown of bitcoin production.
Canaan’s total installed computing power stood at 14.89 EH/s at the end of July, with a further 0.10 EH/s of expected computing power, bringing estimated total computing power to 14.99 EH/s.
The company reported an average all-in electricity cost of 4.3 US cents per kilowatt-hour during July.
For its non-joint-venture operations, Canaan reported average miner efficiency of 17.9 joules per terahash in North America. Globally, non-joint-venture operations had an average efficiency of 23.7 J/TH, while its joint-venture operations recorded 24.8 J/TH.
The scale of Canaan’s installed capacity reflects the company’s expanding footprint in Ethiopia over the past two years.
Its 2025 annual report identified Ethiopia as one of its main mining locations alongside the United States. The company reported four active mining projects in Ethiopia at the end of 2024, with 4.64 EH/s of installed capacity.
By March 2025, the number of projects had fallen to two, although installed capacity stood at 4.22 EH/s. The company subsequently expanded its Ethiopian infrastructure, reporting 4.56 EH/s of installed capacity in November 2025 and 4.99 EH/s in December.
Its operating capacity, however, declined during 2026. Canaan reported 2.20 EH/s of operating capacity in Ethiopia in May, which fell to 0.36 EH/s in June while installed capacity remained at 4.96 EH/s. By July, the company said mining operations in the country had been paused.
The company’s Ethiopian capacity was slightly larger than its operations in the Americas, which had 4.90 EH/s of operating computing power at the end of July. Its other operations included capacity in Canada, Malaysia and the Middle East.
Canaan did not disclose its electricity consumption or bitcoin production specifically for Ethiopia, meaning its July update does not establish how much of its monthly output was generated in the country before the operations were paused.
Canaan said its bitcoin holdings could also become a source of capital for other corporate purposes.
The company recently authorised management to use part of its cryptocurrency treasury to fund share repurchases, saying bitcoin generated from its mining operations could be monetised and redeployed when management considers buybacks attractive.
Canaan Chairman and Chief Executive Nangeng Zhang said the company was seeking to expand beyond bitcoin mining hardware into a more integrated computing and energy platform.
The July figures highlight Ethiopia’s importance to Canaan’s global mining infrastructure, even as the company has temporarily paused operations at its Ethiopian sites. The company has not publicly disclosed the reason for the suspension or provided a timetable for resuming mining.