Ethiopia signed a 184 million US dollar grant agreement with the African Development Bank to accelerate construction of the Adama–Awash expressway, a critical segment of the transport corridor that carries more than 90 percent of the country’s maritime trade through the Port of Djibouti.
The funding, signed on December 10 in Addis Ababa, will finance a 67-kilometre stretch between Melka Jilo and Awash. The section is one of the main missing links in the 130-kilometre Adama–Awash expressway, which extends the Addis Ababa–Adama toll road eastward and is designed to cut travel times, ease congestion and strengthen the logistics backbone of Africa’s second-most populous nation.
“The project reflects Ethiopia’s commitment to regional stability and deeper integration,” Finance Minister Ahmed Shide said at the signing ceremony.
Alex Mubiru (PhD), the AfDB’s Director General for East Africa, co-signed the agreement and said the Bank would continue supporting Ethiopia’s reforms and infrastructure pipeline, including planned investments in major transport and aviation projects.
The Adama–Awash expressway is part of a broader plan to modernise the Ethiopia–Djibouti transport corridor, the main artery for the country’s imports and exports. The route runs parallel to the Djibouti railway and bypasses busy towns including Nura Era, Wolenchiti and Melka Jilo.
Once complete, it will create a seamless, access-controlled, four-lane connection from Addis Ababa to Awash, descending from 1,500 metres near Adama to around 900 metres at its eastern end.
Construction began in 2021 after Prime Minister Abiy Ahmed launched the first 60-kilometre section, financed partly through a USD 95 million AfDB loan. That stretch, built by a joint venture between China Communications Construction Company and local contractor LRBCL, is now nearing completion.
Progress on the expressway has been slower than originally planned. The initial section cost an estimated 154 million US dollar, while resettlement and compensation for affected communities in Oromia and Amhara regions added more than 502 million birr. Hundreds of households were relocated under a Resettlement Action Plan designed to restore livelihoods and support vulnerable groups, including women-headed households.
Land acquisition, environmental clearances and logistical bottlenecks have also contributed to delays, common in Ethiopia’s large-scale transport projects.
Once operational, the expressway is expected to halve travel time between Adama and Awash to about 30 minutes and support daily traffic of more than 20,000 vehicles. The improved link is expected to ease pressure on Route 1, reduce freight costs and strengthen Ethiopia’s export competitiveness. It will also improve access to industrial zones and agricultural centres in central and eastern Ethiopia.
The latest financing follows a meeting between Ahmed Shide and Mubiru—on his first official visit to Ethiopia—where the AfDB signalled ongoing support for Ethiopia’s economic recovery and public-investment agenda. The Bank is also engaging in discussions on budget support and financing for flagship projects such as the planned Ethiopian Airlines Bishoftu Mega Airport.