Ethiopian Electric Utility has begun a nationwide replacement of legacy three-phase meters used by high-load customers as part of its Advanced Metering Infrastructure rollout.
Zerihun Abebe, AMI SCADA project manager, said the new STS-enabled meters were procured after reviewing systems used in other markets. The devices support mobile-based prepaid top-up and provide real-time consumption data through a customer interface unit.
The AMI system records usage levels, credit balances, voltage conditions and outages. It also issues alerts for peak-hour loads, low credit and service interruptions. The meters can be configured and reset remotely, allowing EEU to track network conditions and reduce power losses.
The programme targets the replacement of 80,000 three-phase meters nationwide. So far, 250 devices have been installed across regional centres. Customers are briefed on payment procedures and meter use at the point of replacement.
The project office is overseeing equipment supply and training for field technicians. Zerihun added that tampering with the meters carries legal penalties and encouraged customers to report any faults directly to the utility.
The current phase builds on earlier efforts to replace long-serving electromechanical meters with AMI-compatible units.