Ethiopia is advancing a 4.3 billion birr electricity distribution rehabilitation and capacity expansion project aimed at improving the reliability of power supply in Addis Ababa and the neighbouring city of Sheger.
The fourth phase of the programme involves the reconstruction and upgrading of 703 kilometres of electricity distribution network. The project includes the installation of about 2,000 new transformers with varying capacities and the upgrading of another 2,000 existing transformers to strengthen the grid’s ability to handle rising electricity demand.
The works also cover the reconstruction and improvement of 56 feeder lines extending from power distribution substations, alongside the installation of 62 load break switches designed to regulate electricity flow and manage excess load within the network.
According to project updates, overall physical progress has reached 36.74 percent. So far, 2,857 concrete utility poles have been installed as part of the distribution network upgrade.
Once completed, the project is expected to reduce the frequency of power interruptions along medium-voltage distribution lines by about 27 percent per 100 kilometres annually in Addis Ababa and Sheger. Transformer failure rates are also projected to decline from about three percent to two percent.
The upgraded distribution lines are being constructed using concrete poles and insulated cables designed to improve operational safety and extend the lifespan of the infrastructure.
The project is financed through a loan from the World Bank and forms part of wider electricity distribution rehabilitation and expansion activities under the ADELE project.