The Ministry of Irrigation and Lowlands has reported that budget constraints and regional security threats are jeopardizing the timely completion of key irrigation projects, raising concerns among lawmakers about recurring performance gaps in the sector.
The Ministry disclosed the challenges during a nine-month performance review presented to the House of Peoples’ Representatives (HPR). Officials noted that while some construction milestones have been exceeded, persistent financial shortfalls and instability in certain areas have become major obstacles to meeting scheduled timelines, cost estimates, and quality benchmarks.
In his briefing to parliament, Minister Abraham Belay (PhD) outlined progress in project preparation: feasibility studies were completed for six schemes, study and design work finished for four existing projects, and design revisions carried out for two others.
On infrastructure delivery, Abraham reported that the Ministry surpassed its target of developing 100,000 hectares of irrigable land, achieving 117,100 hectares a performance he described as a fundamental improvement over previous years’ difficulties.
While acknowledging the Ministry’s strategic decision to focus on existing projects rather than initiate new ones during the current budget year, members of parliament pointed to several unresolved shortcomings. Lawmakers specifically cited low execution rates for certain schemes and persistent implementation failures in irrigation developments that have already cleared study and design phases issues they characterized as recurrent.
MPs observed slight recent improvements, but they reiterated that flaws in feasibility studies and project designs have long hampered the sector, a problem the House has repeatedly urged the Ministry to correct.
The legislative body called on the Ministry to maintain its commitment to finishing old projects without adding new ones. They further demanded immediate action to resolve delays in irrigation development, clarity on budget utilization, and detailed updates on project progress.
On the issue of budgetary constraints, MPs advised the Ministry to give special attention to longstanding grievances over fair compensation for community members displaced from their land.
Lawmakers noted that many of the identified gaps and challenges are directly linked to the current budget shortage, reinforcing the Ministry’s position that financial limitations not just planning or execution are a primary constraint.