The World Bank is preparing a 20 million US dollars Foreign Exchange Liquidity Support Mechanism (FLSM) for Ethiopia, aimed at reducing currency risk for independent power producers (IPPs) in the renewable energy sector.
The project, currently at the concept review stage, is designed to ease one of the most persistent constraints to private infrastructure investment in the country: limited and volatile access to foreign exchange.
Disclosed on June 5 via the World Bank’s projects portal, the FLSM would provide the Ministry of Finance with a dedicated, replenishable foreign currency buffer to meet its obligations to IPP developers. The structure is intended to "tide over any short-term gaps" in Ethiopia’s foreign exchange commitments, according to official project documents.
Slated for board consideration in September 2025, the mechanism would be managed by Ethiopia’s Ministry of Finance through its Public-Private Partnership (PPP) Unit. While the total project cost is listed at zero—indicating no direct disbursements for infrastructure—the 20 million US dollars commitment is earmarked exclusively as a liquidity instrument.
The initiative is part of Ethiopia’s strategy to attract private capital into its renewable energy sector, which holds vast untapped potential but has struggled to gain traction due to macroeconomic instability, forex shortages, and investor risk aversion.
“The FLSM will be structured to address the foreign exchange availability risk under suitable replenishment commitment by the Government—essentially providing additional liquidity to the Government to tide over any short-term gaps in meeting its foreign exchange commitments to the IPP developers,” said the World Bank in the project abstract. The effort is scheduled to become operational in fiscal year 2026, pending approval.
The mechanism is not expected to require consultant services and carries a moderate environmental and social risk rating.
Ethiopia has been actively seeking to revamp its energy landscape by introducing bankable PPP models. However, payment delays and currency convertibility concerns have stalled progress on several large-scale renewable projects.
If successful, the FLSM could act as a template for derisking private infrastructure finance in other fragile or low-income markets where forex volatility undermines long-term contract enforcement.